Thursday, November 12, 2009

H & J Progress

Aloha Kakou:

Work continues on H and J buildings as spalling is repaired and handrails are prepped for painting. The current schedule includes power washing of H building tomorrow followed by that building's painting next week. Starting November 30th, painting will begin on J building. That building will be painted in three different sections, with each section taking a week to finish. The painting work is on schedule and, right now, looks to be completed by December 18.



No comments: